   Weekly progress Report as on 25.10.2013
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 25-10-2013.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Progress completed 24/32
2 Pilecap Progress P1- WORK IN PROGRESS.P2 CONCRETED.
3 Pier Not started  
4 Piercap Not started  
5 Girder Not started  
6 Slab Not started  
7 Handrail with kerb Not started  
8 Ex.joint Not started  
9 Tarring work Not started  
10 Service road work Progress aloor right side in progress.
11 Retaining wall work Not started  
       
       
       
       
       
       
       
       
 
Back
 
    
SHUTTERING WORK IN PROGRESS P2.

    
    
REINFORCEMENT WORK IN P1 PILECAP.

    
    
REINFORCEMENT LOWERING IN P5-4.

    
    
PILING STARTED IN P6.

    
 
 
 

 

 

 

 

 

 

 