Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto 11.10.2013 |
Balance work up to 11.10.2013 |
Cumulative delay in Qty up to 11.10.2013 |
Work planned during the week |
Actual work done during the week |
Delay in Qty up to this week |
Work Planned for next week |
1 |
SLAB Pettah side(Approach portion) |
4 |
4 |
0 |
|
|
|
|
|
2 |
SLAB Anayara side(Approach portion) |
4 |
4 |
0 |
|
|
|
|
|
3 |
Service Road Pettah side(Approach portion) |
100% |
100% |
0 |
|
|
|
|
|
4 |
Service Road Anayara side(Approach portion) |
100% |
100% |
0 |
|
|
|
|
|
5 |
RT Wall Pettah side(Approach portion) % |
100 |
100 |
0 |
|
|
|
|
|
6 |
RT Wall Anayara side(Approach portion) % |
100 |
100 |
0 |
|
|
|
|
|
9 |
RE Wall Panel Erection Pettah side(Approach portion) |
400 |
400 |
0 |
|
|
|
|
|
10 |
Expansion Joint(Pettah side) |
4 |
3 |
1 |
|
|
|
|
|
11 |
Expansion Joint(Anayara side) |
4 |
3 |
1 |
|
|
|
|
|
12 |
Friction Slab (Pettah side) |
2 |
2 |
0 |
|
|
|
|
|
13 |
Friction Slab(Anayara side) |
2 |
2 |
0 |
|
|
|
|
|
14 |
Stair Case |
2 |
0 |
2 |
|
|
|
|
1 |
15 |
Painting |
100% |
100% |
0% |
|
|
|
|
|