PROGRESS OF ROB ALOOR-MALA WORK AS ON 11-10-2013. |
|
Description |
Completed/ Progress |
Remarks |
1 |
ROB ALOOR-MALA |
|
|
1 |
Piling |
Progress |
completed 11/32 |
2 |
Pilecap |
Progress |
P1,P2,pile chipping completed. |
3 |
Pier |
Not started |
|
4 |
Piercap |
Not started |
|
5 |
Girder |
Not started |
|
6 |
Slab |
Not started |
|
7 |
Handrail with kerb |
Not started |
|
8 |
Ex.joint |
Not started |
|
9 |
Tarring work |
Not started |
|
10 |
Service road work |
Progress |
aloor right side in progress. |
11 |
Retaining wall work |
Not started |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|