Prevoius Weekly Reports

   12.11.2010
    

 

Si No

Activity Description

Total Quantity

Cumulative progress uptothis week

Balance  work

Cumulative delay in weeks

Work  planned  during the week

Actual work done during the week

Delay for the week

Work  Planned for next week

Remarks

1

PILE SHORNUR SIDE

9

0

9

6

 0

0

0

0

 

2

PILE MED.COLLEGESIDE

36

19

17

6

6

6

0

8

 

3

PILE RAILWAY SPAN

6

 

6

12

0

0

0

 

 

4

PILE CAP SHORNUR SIDE

3

 

3

6

0

0

0

 

 

5

PILE CAP MED.COLLEGESIDE

15

 

15

4

0

0

0

 

 

6

PILE CAP RAILWAY SPAN

2

 

2

6

0

0

0

 

 

7

PIER SHORNUR SIDE

3

 

 

4

0

0

0

 

 

8

PIERMED. COLLEGESIDE

12

 

 

4

0

0

0

 

 

9

PIER RAILWAY SPAN

2

 

 

4

0

0

0

 

 

 
Back
 
    
REMOVING EARTH FOR PILE CAP CASTING

    
    
CONCRETING OF PILE P9 C

    
    
CONCRETING OF PILE P6 B

    
    
CONCRETING OF PILE P 12 B

    
 
    
CONCRETING OF PILE P 6C

    
    
CONCRETING OF PILE P 8 A (08.11.10)

      
 

 

 

 

 

 

 

 