   Weekly Progress Report as on 11.10.2013
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed  
2 PILE PADANNA SIDE 24 24 Completed  
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed  
4 PILE CAP  PADANNA SIDE 8 8 Completed  
5 PIER CHERUVATHOOR SIDE 9 9 Completed  
6 PIER PADANNA SIDE 8 8 Completed  
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed  
8 PIER CAP PADANNA SIDE 8 8 Completed  
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed Friction slab capping complete at both RHS&LHS.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span  
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span  
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0 complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 7 1 0 0 0 0 0 complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed complete for Friction slab also.
16 KERB PADANNA SIDE 100% 100% Completed complete for RE Panel portion also.
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed complete for RE Panel portion also.
18 HANDRAIL PADANNA SIDE 100% 100% Completed complete for RE Panel portion also.
19 Painting 100% 75% 25% 10% 10% 0% 10% 10% Painting at chr side held up due to lack of labourers.
17 BM/BC 100% 30% 70% 40% 10.00% 0.00% 45.00% 10.00% Bitumen Plant repaired,but the works will be started only after Pooja due to lack of labourers and staff.Chr side service road DBM complete.Padanna side traffic areas DBM complete.
18 Others/Miscellaneous                 Drainage works complete for 150 m at chr side.
19 ROAD WORK GSB+WMM Work 90% complete GSB+WMM done for 4m service road extension at chr side from P13 to anganavadi area.
20 Drainage Padanna side 100.00% 10.00% 90.00% 40.00% 15.00% 5.00% 50.00% 15.00% Written instruction was given to the contractor on 19.06.2013.Excavation complete for 40m.Concrete works delaying due to mixer machine complaint and labour shortage.
                    DR Work complete for 4m service road and 7m road chr side.
21 RAILWAY PORTION                 PILING COMPLETE,RP1 PILE CAP COMPLETE,3 piers final lift complete at this location.Pile load test complete.
                    Hume pipe laying complete at chr side to drain off rain water
                     
                     
                     
  Availbility of Men                   
  Date 10/5/2013 10/6/2013 10/7/2013 10/8/2013 10/9/2013 10/10/2013 10/11/2013    
  No of labours 1 0 1 7 2 9 9    
 
Back
 
    
DRAINAGE EXCAVATION PADANNA SIDE

    
    
CHR SIDE SERVICE ROADS DBM COMPLETE

      
 

 

 

 

 

 

 

 