Prevoius Weekly Reports

   Weekly Progress Report as on 04.10.2013
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 19 2          
7 Expansion Joint 21 18 3   1 1 0 0
8 RC wall - Kuttipuram side 100% 100% 0% - 0% 0% 15% 0%
9 RC wall - Kanjipura side 100% 100% 0%   0% 0% 10% 0%
10 BOX culvert 100% 100% 0%   - - - -
11 CC wall kuttipuram side 100% 100% 0%             - 10% 10% 30% 0%
12 E/W  100% 30% 70%   20% 10% 50% 20%
13 HR 100% 75% 25%   5% 5% 0% 0%
                   
Date 9/28/2013 9/30/2013 10/1/2013 10/2/2013 10/3/2013 10/4/2013      
No. of labours 18 18 12 12 12 12      
 
Back
 
    
KUTTIPURAM SIDE IN PROGRESS

    
    
EARTH WORK IN PROGRESS AT NH SIDE

      
 

 

 

 

 

 

 

 