Weekly Reports

Azhimavukadavu River Bridge

Weekly Progress Report - 07.12.2020 to 12.12.2020
 
Weekly Progress Report - 07.12.2020 to 12.12.2020
07.12.2020 08.12.2020 09.12.2020 10.12.2020 11.12.2020 12.12.2020
Piling Work Piling Work Piling Work No work due to election. Piling Work Piling Work
 
  Concreting 13th Pile   Concreting 14th Pile  
           

 

 
Click here to view Previous Reports
 
    
CONCRETE

    
    
PILING

    
    
PILING

    
    
PILING

    
    
PILE CONCRETING

    
    
PILING

    
    
PILING

    
 
 

 

 

 

 

 

 

 