   Weekly progress report as on 04.10.2013
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 04-10-2013.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Progress completed 14/32
2 Pilecap Not started  
3 Pier Not started  
4 Piercap Not started  
5 Girder Not started  
6 Slab Not started  
7 Handrail with kerb Not started  
8 Ex.joint Not started  
9 Tarring work Not started  
10 Service road work Not started  
11 Retaining wall work Not started  
       
       
       
       
       
       
       
       
 