Prevoius Weekly Reports

   12.11.2010
    

 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to previous week

Balance  work

Cumulative delay in weeks after

Spplagmnt

Work  planned  during the week

Actual work done during the week

Short fall in the week 

Work  Planned for next week

Remarks

1

Re wall towards NH side

100%

0

100

32

0

0

0

0

 

2

RE wall towards Pulikkakadauside

100%

98

2

12

2

0

2

2

Workobstructed due to rain

3

Approach

 Span

5 No

4

1

20

-

-

-

-

 

4

Railway

 span

3No

0

0

19

 

 

 

 

Design Approval pending from railways

 

5

Pile (RlY)

18No

0

0

39

 

 

 

 

 

9

Piers (Rly)

4No

0

0

29

 

 

 

 

 

10

 

Handrail

 

846m

15m

835

 

 

 

 

 

 

11

Kerb

423m

81

342

-

 

 

 

 

 

12

Road work

100%

0

0

 

 

 

 

 

 

13

Friction slab

2  Nos

PCClaying

Slab  work

 

 

PCClaying

 

 

 

Slab work

 

 

14

Approachslab

2 No

PCClaying of  one Approach slab

Slab  work

49

PCClaying of  one Approach slab

PCC Laying

 

 

 

 

 

 
Back
 
    
RAILWAY TRAFFIC SIGNAL CABLES ARE LYING IN THE ROB ALIGNMENT(9.11.2010)

    
    
REINFORCEMENT FOR APPROACH SLAB TOWARDS PULIKKAKKAKADAVU SIDE(12.11.2010)

    
    
PCC LAYING FOR APPROACH SLAB TOWARDS PULIKKAKKAKADAVU SIDE(11.11.2010)

    
    
JOINT INSPECTION WITH SECTION ENGINEER ,SOUTHERN RAILWAYS,THRISSUR TO LOCATE SIGNAL CABLES(9.11.2010)

    
 
    
CASTING OF HAND RAIL TOWARDS PULIKKAKKADAVU SIDE(10.11.2010)

      
 

 

 

 

 

 

 

 