SlNo
Activity -Description
Total Quantity
Cumulative progress up to previous week
Balance work
Cumulative delay in weeks after
Spplagmnt
Work planned during the week
Actual work done during the week
Short fall in the week
Work Planned for next week
Remarks
1
Re wall towards NH side
100%
0
100
32
2
RE wall towards Pulikkakadauside
98
12
Workobstructed due to rain
3
Approach
Span
5 No
4
20
-
Railway
span
3No
19
Design Approval pending from railways
5
Pile (RlY)
18No
39
9
Piers (Rly)
4No
29
10
Handrail
846m
15m
835
11
Kerb
423m
81
342
Road work
13
Friction slab
2 Nos
PCClaying
Slab work
14
Approachslab
2 No
PCClaying of one Approach slab
49
PCC Laying