   Weekly Progress Report as on 27.09.2013
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 27-09-2013.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Progress completed 11/32
2 Pilecap Not started  
3 Pier Not started  
4 Piercap Not started  
5 Girder Not started  
6 Slab Not started  
7 Handrail with kerb Not started  
8 Ex.joint Not started  
9 Tarring work Not started  
10 Service road work Not started  
11 Retaining wall work Not started  
       
       
       
       
       
       
       
       
 
Back
 
    
PILING WORK STARTED IN A1 LOCATION,IN EX_ROAD.

      
 

 

 

 

 

 

 

 