   Weekly Progress Report as on 20.09.2013
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed  
2 PILE PADANNA SIDE 24 24 Completed  
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed  
4 PILE CAP  PADANNA SIDE 8 8 Completed  
5 PIER CHERUVATHOOR SIDE 9 9 Completed  
6 PIER PADANNA SIDE 8 8 Completed  
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed  
8 PIER CAP PADANNA SIDE 8 8 Completed  
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed Friction slab capping complete at both RHS&LHS.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span  
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span  
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0 complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 7 1 0 0 0 0 0 complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed complete for Friction slab also.
16 KERB PADANNA SIDE 100% 100% Completed complete for RE Panel portion also.
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed complete for RE Panel portion also.
18 HANDRAIL PADANNA SIDE 100% 100% Completed complete for RE Panel portion also.
19 Painting 100% 65% 35% 20% 10% 10% 0% 10% PAINTING IP AT CHR SIDE.First coat complete for handrails.
17 BM/BC 100% 0 100% 30 30.00% 10.00% 20.00% 20.00% DBM works progressing very slowly due to frequent rains.Mastic asphalt complete at both sides.
18 Others/Miscellaneous                 Drainage works complete for 150 m at chr side.
19 ROAD WORK GSB+WMM Work 90% complete GSB+WMM done for 4m service road extension at chr side from P13 to anganavadi area.
20 Drainage Padanna side 100.00% 0.00% 100.00% 10.00% 15.00% 0.00% 15.00% 15.00% To be started this week,shortage of labour delays the start.
                    DR Work complete for 4m service road and 7m road chr side.
21 RAILWAY PORTION                 PILING COMPLETE,RP1 PILE CAP COMPLETE,3 piers first lift complete at this location.
                    Hume pipe laying complete at chr side to drain off rain water
                     
                     
                     
  Availbility of Men                   
  Date 14-09-2013 15-09-2013 16-09-2013 17-09-2013 18-09-2013 19-09-2013 20-09-2013    
  No of labours 15 15 5 5 12 12 12    
                     
  Material Stocking Status Required Available Remarks            
  Coarse Aggreagate (m3) available              
  Fine Aggreagate(m3) available            
  Cement(bag) 0 15            
  Steel(MT) 0 0.3            
 
Back
 
    
RAILWAY PORTION PILE LOAD TEST ARRANGEMENTS IP

    
    
DBM FIRST LAYER IP AT CHR SIDE

      
 

 

 

 

 

 

 

 