Prevoius Weekly Reports

   Weekly progress report as on 13.09.2013
    
Progress as on 13-9-13
  Description Completed/ Progress Remarks
  ROB Kainatty (P6-RP4)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder Not started concreting is delayed due to repairing of pump
8 Shuttering work for deck slab Not started  
9 Reinforcement binding of deck slab Not started  
10 Deck slab concrete Not started  
11 MISCELLANEOUS WORK Not started  
11(a) Concreting of kerb, handrails Not started  
11(b) Expansion joints Not started  
12 ROAD WORK Not started  
12(a) Aplplying mastic Asphault Not started  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK Not started  
 
  Description Completed/ Progress Remarks
  ROB Kainatty (P5-RP1)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder In progress 20 percent completed
6 Shuttering work for girder Not started  
7 Concreting of girder Not started  
8 Shuttering work for deck slab Not started  
9 Reinforcement binding of deck slab Not started  
10 Deck slab concrete Not started  
11 MISCELLANEOUS WORK Not started  
11(a) Concreting of kerb, handrails Not started  
11(b) Expansion joints Not started  
12 ROAD WORK Not started  
12(a) Aplplying mastic Asphault Not started  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK Not started  
 