   Weekly progress Report as on 06.09.2013
    
Progress Report For Kumaranalloore ROB for the week ending on 06-09-2013  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE 33 33 0 0 0 0 0       pile completed
2 PILE CAP 11 11 0 0 1 1 0       pile cap completed
3 PIER 11 10 1 0 0 0 0 1   shuttering work at P5
4 PIER CAP 11 8 3 0 2 1 0 1   Reinforcement work at P7
5 LOAD TEST 1 1 0 0 0 0 0     Load test completed
6 SLAB 10 3 7 0 1 0 0     Slab P3-P4 , P9-AP2 staging & reinforcement work
7 PEDESTAL 9 7 2 0 0 0 0      
                       
 