Progress as on 30-8-13 |
|
Description |
Completed/ Progress |
Remarks |
|
ROB Kainatty (P6-RP4) |
|
|
1 |
Levelling and consolidation of the ground for staging work |
completed |
|
2 |
Staging work |
completed |
|
3 |
Reinforcement bending work |
completed |
|
4 |
Bottom shuttering work for girder |
completed |
|
5 |
Reinforcement binding for girder |
completed |
|
6 |
Shuttering work for girder |
completed |
Arrangement of concrete in progress |
7 |
Concreting of girder |
Not started |
|
8 |
Shuttering work for deck slab |
Not started |
|
9 |
Reinforcement binding of deck slab |
Not started |
|
10 |
Deck slab concrete |
Not started |
|
11 |
MISCELLANEOUS WORK |
Not started |
|
11(a) |
Concreting of kerb, handrails |
Not started |
|
11(b) |
Expansion joints |
Not started |
|
12 |
ROAD WORK |
Not started |
|
12(a) |
Aplplying mastic Asphault |
Not started |
|
12(b) |
Applying bituminous concrete |
Not started |
|
13 |
PAINTING WORK |
Not started |
|
|
|
Description |
Completed/ Progress |
Remarks |
|
ROB Kainatty (P5-RP1) |
|
|
1 |
Levelling and consolidation of the ground for staging work |
completed |
|
2 |
Staging work |
In progress |
Done 50% |
3 |
Reinforcement bending work |
Not started |
|
4 |
Bottom shuttering work for girder |
Not started |
|
5 |
Reinforcement binding for girder |
Not started |
|
6 |
Shuttering work for girder |
Not started |
|
7 |
Concreting of girder |
Not started |
|
8 |
Shuttering work for deck slab |
Not started |
|
9 |
Reinforcement binding of deck slab |
Not started |
|
10 |
Deck slab concrete |
Not started |
|
11 |
MISCELLANEOUS WORK |
Not started |
|
11(a) |
Concreting of kerb, handrails |
Not started |
|
11(b) |
Expansion joints |
Not started |
|
12 |
ROAD WORK |
Not started |
|
12(a) |
Aplplying mastic Asphault |
Not started |
|
12(b) |
Applying bituminous concrete |
Not started |
|
13 |
PAINTING WORK |
Not started |
|