Si No
Activity Description
Total Quantity
Cumulative progress upto last week
Balance work
Cumulative delay in weeks
Work planned during the week
Actual work done during the week
Delay for the week
Work Planned for next week
Remarks
1
PILE CALICUT SIDE
27
12
2
PILE NH SIDE
36
8 piles
4
9
No workers due to Deepavali
3
PILE RAILWAY SPAN
16
11
PILE CAP CALICUT SIDE
8
5
PILE CAPNH SIDE
6
PILE CAP RAILWAY SPAN