   Weekly Progress Report as on 16.08.2013
    
Progress as on 17-8-13
  Description Completed/ Progress Remarks
  ROB Kainatty (Adjacent span)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work In progress Done 90%
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder Not started  
6 Shuttering work for girder Not started  
7 Concreting of girder Not started  
8 Shuttering work for deck slab Not started  
9 Reinforcement binding of deck slab Not started  
10 Deck slab concrete Not started  
11 MISCELLANEOUS WORK Not started  
11(a) Concreting of kerb, handrails Not started  
11(b) Expansion joints Not started  
12 ROAD WORK Not started  
12(a) Aplplying mastic Asphault Not started  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK Not started  
 
Back
 
    
REINFORCEMENT OF PEDESTAL

    
    
STAGING WORKS IN PROGRESS

      
 

 

 

 

 

 

 

 