Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886108
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Projects

  Weekly Progress Weekly Progress Reports   |   Photo gallery Photo Album
Feroke ROB
 
Name ROB at Feroke 
District Kozhikkode
Administrative Sanction Details GO(Rt)No.454/2017/PWD dated 31.03.2017
Funding details Government Funding
AS amount 19.01 Crores
Length including approaches 575 m
Right of Way of Bridge 12.5 m to 7.5 m
Present Status Fresh requisition for acquisition of three remaining cases (out of 37) is submitted to District Collector on 26.06.2019. SIA final report published. Expert committee formed on 03.03.2020. Expert Committee evaluation report is progressing.
 

 

 

 

 

 

 

 

 

 