Prevoius Weekly Reports

   29.10.2010
    
 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to previous week

Balance  work

Cumulative delay in weeks after

Spplagmnt

Work  planned  during the week

Actual work done during the week

Short fall in the week 

Work  Planned for next week

Remarks

1

Re wall towards NH side

100%

0

100

31

0

0

0

0

 

2

RE wall towards Pulikkakadauside

100%

93

7

11

5

5

0

2

 

3

Approach

 Span

5 No

4

1

19

-

-

-

-

 

4

Railway

 span

3No

0

0

18

 

 

 

 

Design Approval pending from railways

 

5

Pile (RlY)

18No

0

0

38

 

 

 

 

 

9

Piers (Rly)

4No

0

0

28

 

 

 

 

 

10

 

Handrail

 

846m

0

0

 

 

 

 

 

 

11

Kerb

423m

81

342

-

 

 

 

 

 

12

Road work

100%

0

0

 

 

 

 

 

 

14

Approachslab

2 No

0

0

47

 

 

 

1

 

 

                 
                   
                   
                   
                   
                   
                   
                   
                   
                   
                   
                   
                   
                   
                   

 

 
Back
 
    
2RETAINING WALL TOWARDS PULIKKAKKADAVU SIDE

    
    
1JOINT INSPECTION WITH RAILWAY OFFICIALS

      
 

 

 

 

 

 

 

 