Prevoius Weekly Reports

   Weekly Progress Report as on 02.08.2013
    
Progress Report For Kumaranalloore ROB for the week ending on 02.08.2013  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE 33 33 0 0 0 0 0      
2 PILE CAP 11 10 1 0 o 0 0      
3 PIER 11 9 2 0 1 0 0 1   P7 1st lift completed
4 PIER CAP 11 7 4 0 1 0 0 2   Reinforcement works going on
5 LOAD TEST 1 1 0 0 0 0 0     Load test completed
6 SLAB 10 2 8 0 1 1 0     Slab P1-P2 concreted
                      Work is delayed due to heavy rain
                       
 