Si No
Activity Description
Total Quantity
Cumulative progress upto this week
Balance work
Cumulative delay in weeks
Work planned during the week
Actual work done during the week
Delay for the week
Work Planned for next week
Remarks
1
PILE TRIKARIPPUR SIDE
24
9
15
4
0
3
6
2
PILE EZHIMALA SIDE
36
PILE RAILWAY SPAN
10
PILE CAP PAYYANNUR SIDE
27
5
PILE CAP TRIKARIPPUR SIDE
PILE CAP RAILWAY SPAN
7
PILE CAP EZHIMALA SIDE
12
8
PIER RAILWAY SPAN
PIER TRIKARIPPURT SIDE
11
PIER EZHIMALA SIDE
PIER PAYYANNUR SIDE