Prevoius Weekly Reports

   29.10.2010
    

Si No

Activity Description

Total Quantity

Cumulative progress upto this week

Balance  work

Cumulative delay in weeks

Work  planned  during the week

Actual work done during the week

Delay for the week 

Work  Planned for next week

Remarks

1

PILE TRIKARIPPUR SIDE

24

9

15

4

 0

3

1

6

 

2

PILE EZHIMALA SIDE

36

 

36

4

0

0

0

   

3

PILE RAILWAY SPAN

6

 

6

10

0

0

0

   

4

PILE CAP PAYYANNUR SIDE

27

 

27

4

0

0

0

   

5

PILE CAP TRIKARIPPUR SIDE

6

 

 

2

0

0

0

   

6

PILE CAP RAILWAY SPAN

2

 

 

4

0

0

0

   

7

PILE CAP EZHIMALA  SIDE

12

 

 

2

0

0

0

   

8

PILE CAP PAYYANNUR SIDE

9

 

 

2

0

0

0

   

9

PIER RAILWAY SPAN

2

 

   

0

0

0

   

10

PIER TRIKARIPPURT SIDE

6

 

   

0

0

0

   

11

PIER EZHIMALA SIDE

12

 

   

0

0

0

   

12

PIER PAYYANNUR SIDE

9

 

   

0

0

0

   
                 
                   
                   
                   
                   
                   
                   
                   
                   
                   
 