   Weekly Progress Report as on 26.07.2013
    
Progress Report For Kumaranalloore ROB for the week ending on 26-07-2013
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE 33 33 0 0 0 0 0    
2 PILE CAP 11 10 1 0 o 0 0    
3 PIER 11 9 2 0 1 0 0 1  
4 PIER CAP 11 7 4 0 1 0 0 1  
5 LOAD TEST 1 1 0 0 0 0 0    
6 SLAB 10 1 9 0 1 0 0 1  
                     
                     
 
Back
 
    
SLAB CONCRETING AT AP1-P1 SPAN

    
    
STAGING WORK AT AP1- P1 SPAN

    
    
P1-P2 SPAN

      
 

 

 

 

 

 

 

 