   Weekly progress as on 26.07.2013
    
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards Kadukutty side 27 27 0 0 0 0 0 0  
2 Pile towards Divine Centre side 18 18 0 0 0 0 0 0  
3 Pile cap at Kadukutty  Side 8 8 0 0 0 0 0 0  
4 Pile Cap at Divine centreside 5 5 0 0 0 0 0 1  
5 RC wall at Kadukutty side 100% 0% 100% 0 0% 0% 0 0%  
6 RC wall at Divine centre side 100% 5% 95% 0 5% 5% 0 5%  
7 Pier at Kadukutty Side 8 8 0 0 0 0 0 0  
8 Pier at Divine centre Side 5 5 0 0 0 0 0 0  
9 Piercap at Kadukutty Side 8 8 0 0 0 0 0 0  
10 Piercap at Divine centre 5 4 1 0 0 0 0 1  
11 PEDESTAL 48 36 12 0 0 0 0 4  
12 Beam and cross beam at Kadukutty side 7 4 3 0 0 0 0 0 reinforcement work of p3 p4
13 Beam and cross beam at Divine centre side  4 0 4 0 1 1 0 0 p7 p8
14 Deck slab  at Kadukutty side  7 4 3 0 0 0 0 0  
15 Deck slab  at Divine centre side  4 0 4 0 0 0 0 1 reinforcement slab can finish
16 Dirt wall  2 0 2 0 0 0 0 0  
17 Kerb Kadukutty side 100% 8% 92% 0% 8% 8% 0% 8% p1 p2  and a1 p1 finished
18 Kerb Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
19 Earth filling in approach embankment  100% 0% 100% 0% 0% 0% 0% 0%  
20 Hand rail fixing -Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
21 Hand rail fixing -Kadukutty side 100% 0% 100% 0% 8% 8% 0% 15% a1 p1 and p1 p2
22 Expansion Joints 12 0 12 0% 0% 0% 0% 8%  
23 WBM  100% 0% 100% 0 0% 0% 0% 0%  
24 Acrylic Elastomeric Membrane Coating 100% 0% 100% 0 0% 0% 0% 0%  
                     
Date 20/7/2013 22/7/2013 23/7/2014 24/7/2015 25/7/2016 26/7/2017        
Climate rainy warm warm warm rainy rainy        
No.of labours 69 78 78 80 80 80        
 
Back
 
    
P7 P8 GIRDER CONCRETE

    
    
RC WALL DIVINE SIDE

    
    
P1 P2 HANDRAIL

      
 

 

 

 

 

 

 

 