Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886119
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Projects

  Weekly Progress Weekly Progress Reports   |   Photo gallery Photo Album
KIIFB Projects At a Glance
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

KIIFB PROJECTS

SL

No.

Project Name Status
1 Kundannoor Flyover All the Substructure and Super Structure works Completed
Retaining wall works at Aroor side in Progress
Gabion wall at Aroor side in Progress
Earth Work- Approach road filling at Vytila side in progress
92% completed
2 Edappal Flyover Pile -40/40 completed
Pilecap 9/9 Completed
Pier 7/7 Completed
Pier head-2/2 completed
Girder- Reinforcement works in progress
3 CUSAT
Package 1   (Kalamassery Main Campus Work)
Agreement executed on 05.09.2019
Column Concreting - 16 Nos. completed 
Grade Beam concreting at Zone B - 95% completed
PCC for grade beam concreting  - 100% completed 
Footing concreting  - 100%  completed 
PCC for grade beam - 100% completed
International Guest House
Footing concreting  - 100%  completed 
PCC for grade beam - 100% completed
 Campus Rejunation - Site survey work in progress
4 CUSAT
Package 2 (Ernakulam Lake side Campus Work)
Structural Works- 98%
Block Work- 98%
Internal Plastering- 90%
External Plastering- 90%
Flooring Work- 25%
Painting Work- 30%
Electrical Work- 50%
Plumbing Work- 50%
5 CUSAT
Pacakge 3 (Upgradation of Electrical System110KV)
TS Committee convened
6 CUSAT
Package 4(Solar Roof Top Energy Harvesting)
Work tendered
7 CUSAT
Package 5 (Swimming Pool)

 LOA issued on 29.02.2020
8  Kundara Pallimukku ROB

LA requisition submitted to Dt. Collector Kollam on 07.07.2017.
L.A boundaries marked but Planting of stones interrupted by public.
In the meeting convened by Hon' PWD minister in the presence of Hon Finance Minister it was decided to construct the combined ROB & Flyover at Pallimikku on NH.

Project held up for the decision regarding NH proposal.GAD approved

9  Akathethara-Nadakkavil ROB LA funds deposited to LAO.
Award passed.
In 15 cases cheque issued.
Balance 16 cases cheque not issued due to non production of document. 
10  Idava ROB LA requisition submitted to District Collector, Thiruvananthapuram on 13.07.2017.
Modified LA requisition submitted on 29.08.2018.
Draft RR package is ready for sending LRC's approval.
LA fund request of Rs. 48473295/- sanctioned by MD and uploaded in the KIIFB site.
11  Kottikkulam ROB LA requisition submitted to District Collector Kasargod on13.07.2017.
Awaiting reply from Railways.
Letter sent to Principal Secretary, Transport Dept, Govt of Kerala towards getting construction permission from Railways.
12  Iravipuram ROB Draft RR pakage submitted to LRC on 15.05.2020.
 LA fund deposited to LAO on 14.05.2020.
Awaitin for DD.
13  Koduvally - Illikkunnu ROB LA requisition submitted to Dt. Collector Kannur on 06.07.2017. The entire land acquired except Girijas possession.
14  Vadanumkurissi ROB LA requisition submitted on 28.04.2017. Fund received. Documentation under preperation. LA in final satge.
15  Chelari-Chettippady ROB

LA requisition submitted to Dt. Collector Malapuram on 13.09.2017.

LA fund deposited to LAO. LA in final stage.

16 Pudukkad ROB

LA requisition submitted to Dt. Collector Trissur on 09.10.2017.
Modified requisition submitted to DC on 01.11.2019.

Application forwarded to obtain sanction for conversion of wet land on 07.02.2020.
Correction on GAD required by Railways on 05.02.2020.

17  Maliyekkal ROB LA requisition submitted to Dt. Collector Kollam on 06.10.2017.
The entire land documentation completed except 0.02 Ares possession.
It will not affect the construction of ROB.
It is negligible one. 
18 Chirangara ROB LA requisition submitted to Dt. Collector Trissur on 07.10.2017.
Awaiting fund for publishing DD.
19 Vaduthala ROB LA requisition submitted to Dt. Collector Ernakulam on 23.08.2017.
GAD in tracing sheet submitted to Railway on 11.02.2020.
Chief Engineer (Construction), Railways has informed that LA may be taken up after obtaining final approval of GAD.
20  Tanur Town-Theyyala ROB LA requisition submitted on 13.09.2017.
LA fund deposited to LAO.
DD under preperation.
LA in final stage.
21 Angamaly Kochi airport Bypass

LA requisition submitted to District Collector, Ernakulam on 27.10.2018.
 Due to issues regarding the sanctioned alignment,

RBDCK has requested KIIFB to reconsider the original alignment proposed by RBDCK.
DPR approved on 12.02.2020

22 Thirunavaya- thavanur River Bridge LA requisition submitted to District Collector Malappuram on 13.09.2017.
RR package submitted by District Collector Malappuram to Land Revenue Commissioner.
 19(1) declaration awaited. 
23 Purayar ROB  LA requisition submitted on 28.06.2018.
The balance contigency charge Rs.1076723/- released to LAO on 28.01.2020.
Awaiting 4(1) notification.
24  Chirayinkeezhu ROB LA completed. GAD in tracing sheet submitted to Railway on 11.02.2020.
Tendering put on hold, awaiting decision regarding combined tendering of 10 ROBs.
DD published.
Award enquiry pending.
25 Perumbavoor Bypass LA requisition submitted to Dt. Collector Ernakulam on 22.02.2018.
Expert committee formed.
 11(1) notification awaited.
26 Guruvayoor Kizhakkenada ROB

LA requisition submitted to Dt. Collector Trissur on 03.11.2017.

LA fund deposited to LAO. Awaiting for DD.

27  Melechovha underpass LA requisition submitted to Dt. Collector Kannur on 17.02.2018.
11(1) notification published on 12.11.2019.
Draft RR might be prepared and sent to LRC for approval.
28 South Bazar Flyover LA requisition submitted to District Collector and AS request submitted to Revenue department on 11.12.2019.
Stone planting process is progressing. 
Contingency charge request received.
Steps are being taken for its release from KIIFB.
29 Oradumpalam - Vylongara Bypass Road  LA requisition submitted on 12.07.2018.
Boundary stone planting obstructed by public.
6(1) Notification prepared for publication and sent for publication on 02.09.2019
30 Ettumanoor Flyover  LA requisition submitted on 5.09.2018.
Due to protest from Land Owners. Deputy Collector, Kottayam has directed to proceed with the boundary stone planting.
Letter sent to KITCO on 30.11.2019 to inform us an earliest date to commence the stone planting works with Police protection.
31 Perambra Bypass  LA requisition submitted to Dt. Collector Kozhikode on 20.02.2018.
 Detailed survey is completed and 19(1) to be published.
Draft RR package sent by DC to LRC for approval on 03.03.2020 
32 Koduvally Siraj Flyover  LA requisition submitted on 12.07.2018.
Expert Committee report submited.
11(1) notification awaiting.
33 Kodumanda ROB LA requisition submitted on 17.05.2018.
 But directed to put on hold.
 LA procedure for want of finalisation of GAD.
34 Kanjirapalli Bypass LA requisition submitted on 29.08.2018.
 11(1) notification published on 04.12.2019.
Fund request received .
35 Ottappalam Bypass LA requisition submitted on 04.09.2018.
SIA public hearing conducted on 17.02.2020.
Draft report awaiting. 
36 Koduvayoor Bypass LA requisition submitted to District Collector, Palakkad on 15.01.2019.
Stone planting completed on 26.02.2020.
Joint inspection conducted on 29.02.2020.
 SIA appointed.
Public hearing postponed during lockdown.
37 Kasargod Bypass LA requisition submitted on 15.01.2019.
MLA has informed that there is wide protest from local people on the project and requested for a substitution project. 
Project put on hold.
Principal Secretary directed to submit a report on difficulties to acquire the land for the Bypass. 
Letter sent to govt. on 02.09.2019 for dropping the project as suggested by the MLA.
38 Airport Seaport Road Kalamssery Aluva phase II section a package & III( Nad to Mahilalayam) LA requisition submitted to District Collector.
AS for LA received as per GO(Rt) 1176/2019/Rev TVM dated 22.05.2019.
Survey works started. But stopped due to outbreak of Covid-19.
Contigency Charge 50 lakhs deposited  to LAO.
39 Vallapuzha ROB LA requisition submitted on 16.08.2019.
Boundary Stone Planting completed on 21.01.2020.
GAD Approved & Estimate for approach portion submitted to Railways for approval on 29.11.2019
40 Kuruppanthara ROB LA requisition submitted on 12.07.2018.
Awaiting 11(1) notification.
41 Kuttiyadi Bypass Survey works for planting boundary stone started on 24.09.2019 and interrupted by public.
 A meeting was conducted at the office of KIIFB on 12.12.2019 and decided to modify the alignment as suggested by MLA.
Modified alignment report sent to KIIFB for approval on 27.01.2020
42 Atlantis Railway Over bridge LA Requisition submitted to DC on 15.02.2019.
Work Order issued for planting of Boundary stone.
Boundary of acquired land to be obtained from Cochin Corporation.
43 Nandikkara ROB LA requisition submitted to DC on 11.10.2019.
GAD is under correction, as requested by Railways on 07.01.2020.
Chief Engineer ( Construction), Railways has informed that LA may be taken up after obtaining final approval of GAD.
 Work order issued to the contractor for planting boundary stone.
44  Mayyanad ROB  Boundary stone planting completed.
Joint inspection conducted on 8.8.2019.
Land of 3 SC Family is included in the alignment.
For the rehabilitation, land for these families  has to be find out and requisition has to be submitted for the land.
Hence joint inspection conducted on 12/12/2019.  
For this purpose KITCO had submitted a plan.
 It is being processed.
45 Kallumthazham Junction ROB LA requisition submitted 04.10.2019.
Work order issued to the contractor for planting boundary stone.
GAD not received.
46 Mambrakunnel ROB (Krishnapuram) LA requisition submitted to District Collector on 24.12.2018.
Public hearing held on 31.01.2020.
SIA final report received.
 Expert Committee to be appointed.
47 Kadathuruthi ROB

LA requisition submitted to District Collector on 18.11.2019
Work order issued to contractor for planting boundary stones.

GAD not approved.

48 Nedupuzha ROB LA requisition submitted to District Collector Trissur on 22.01.2019.
Missing stone planting completed.
50 lakhs deposited to LAO for Contigency Charge.
 Awaiting 4(1) notification.
49  Puthiyakavu Chakkuvalli ROB LA Requisition submitted to District Collector on 18.12.2019.
SIA appointed on 03.01.2020.
50 Berricheri ROB

LA requisition submitted to District Collector on 11.06.2019. 

Rev (B) sanction obtained as per GO (Rt) No. 1578/2019/RD dt. 21.06.2019.
 GAD approval awaiting.

51  (Harippad and Cheppad) Nangiyarkulangara ROB  LA Requisition submitted to District Collector on 11.03.2019.
Work Order issued to the Contractor for  planting boundary  stone.
52  Quilandi and Tikkotti ROB- Muchukkunnu ROB DPR approved by KIIFB on 07.02.2020.
LA plan under preperation.
53 Chungam Gate ROB DPR approved by KIIFB on 07.02.2020.
LA plan under preperation.
54 Kozhikkal ROB DPR approved by KIIFB on 07.02.2020.
LA plan under preperation.
55 Hosangadi ROB DPR approved by KIIFB on 10.02.2020.
LA plan under preperation.
56  Azhiyur ROB DPR approved by KIIFB on 10.02.2020.
LA plan under preperation.
57  Edachakai Nadakkavu ROB DPR approved by KIIFB on 10.02.2020.
LA plan under preperation.
58   Uduma ROB DPR approved by KIIFB on 11.02.2020.
LA plan under preperation.
59 Flyover at Railway Junction in Changanacherry Bye-pass DPR approved by KIIFB on 11.02.2020.
LA plan under preperation.
60 Uttara Bridge & Uttara ROB DPR approved by KIIFB on 11.02.2020.
LA plan under preperation.
61  Kushal Nagar ROB DPR approved by KIIFB on 11.02.2020.
LA plan under preperation.
62 Malapuram Police Station Kizhakkethala Chethupalam Flyover DPR approved by KIIFB on 11.02.2020.
LA plan under preperation.
63 Poliyathode kottikada ROB DPR under KIIFB review 
64 SN College ROB DPR under KIIFB review 
65  Temple Road ROB DPR under KIIFB review 
66 Mynagapalli ROB DPR under KIIFB review 
67 Vettu Road ROB DPR under KIIFB review 
68 Ollal ROB DPR under KIIFB review 
69 Kureekad ROB DPR under KIIFB review 
70 Kallumala ROB DPR under KIIFB review 
71  Alathur ROB DPR under KIIFB review 
72  Punnol ROB DPR under KIIFB review 
73  Ezhupunna ROB DPR under KIIFB review 
74  Punnamood ROB DPR under KIIFB review 
75  Manjeshwar ROB DPR under KIIFB review 
76 Nelliyadikadavu ROB DPR under KIIFB review 
77 Moru Glass Gate ROB DPR under KIIFB review 
78 Payyoli ROB DPR under KIIFB review 
79  Trikaripur ROB DPR under KIIFB review 
80 Ponnani Harbour – Padinjarekara Bridge (Cable Stayed) DPR under KIIFB review 
81 Amalapuri ROB DPR under preparation
82 Venkulam ROB DPR under preparation
83 Clay gate ROB DPR under preparation
84 Kaniyapuram ROB DPR under preparation
85 Sarkara ROB DPR under preparation
86 Manjadimoodu ROB DPR under preparation
87 Balaramapuram ROB DPR under preparation
88 Nalukody ROB DPR under preparation
89 Ollur main gate ROB DPR under preparation
90 Nellayi gate ROB DPR under preparation
91 Ernakulam South ROB widening DPR under preparation
92 Attakulangara Flyover DPR under preparation
93 Kanhangad Flyover DPR under preparation
94 Tirur Chamravattom DPR under preparation
95 Vathuruthy ROB DPR under preparation
96 Pandaraparambu undodikadavu DPR under preparation
97 Kizhakkekkotta & Kokkala Flyover DPR under preparation
98 Iringal Mooradu ROB DPR under preparation
99 Thamarassery- Chungam link Road DPR under preparation
 

 

 

 

 

 

 

 

 

 

Untitled Document