Weekly Progress Report - 07.12.2020 to 12.12.2020 |
07.12.2020 |
08.12.2020 |
09.12.2020 |
10.12.2020 |
11.12.2020 |
12.12.2020 |
SS handrail work at fourth floor fire stair
|
SS handrail work at fifth floor fire stair |
SS handrail work at fifth floor fire stair
|
SS handrail work at fifth floor fire stair |
Electrical earthing work at terrace floor.
|
Aluminum fixed window works.
|
Aluminum door frame works. |
Aluminum fixed frame works. |
Aluminum fixed frame works. |
Aluminum fixed frame works. |
SS work at fire stair. |
SS work at fire stair. |
Excavation works for external plumbing and DG foundation. |
External trenching works for plumbing. |
External trenching works for plumbing. |
External trenching works for plumbing. |
Aluminum Louvre work. |
Fire alarm cabling work. |
HVAC works and Electrical cable works . |
HVAC works and Electrical cable works . |
HVAC works and Electrical cable works . |
HVAC works and Electrical cable works . |
HVAC and Plumbing Works |
ELV cable tray works. |
External painting at east side.
|
External painting at north side.
|
External painting at north side. |
External painting at north side. |
External painting at north side. |
Plumbing and painting works |