Weekly progress report as on 12.07.2013 |
All the works of approach span except connecting spans to railway span are completed.Connecting spans can becompleted only after the completion of railway spans which is to be done by Southern Railways. Balance work has been tendered and Letter of Acceptance has been issued. | |