Weekly Progress Report - 07.12.2020 to 12.12.2020 |
07.12.2020 |
08.12.2020 |
09.12.2020 |
10.12.2020 |
11.12.2020 |
12.12.2020 |
Shuttering works/Reinforcement installation for Columns, Lift wall at Zone A, Zone B (GF-FF).
|
Concreting works for Columns, Lift wall at Zone A, Zone B (GF-FF). |
Form Work Installation, Reinforcement work and Shuttering Work in Academic Block
|
No work due to election |
Academic Block - Rebar, Formwork and shuttering works |
Academic Block - Rebar, Formwork and shuttering works |
Form-work preparation/installation for slab at 5.10m level at Zone B. |
Form-work preparation/installation for slab at 5.10m level at Zone B. |
Form-work preparation/installation for slab at 3.30 m level in International Guest House |
|
Engineering Building - Shuttering works for Columns (FF-Roof) |
Engineering Building - Shuttering works for Columns (FF-Roof) |
Shuttering works / Reinforcement installation for First floor Columns (Engg. Building) |
Shuttering works / Reinforcement (Academic block & Engg. Building) |
Reinforcement installation for drain in stretch 1-2.(Campus Rejuvanation)
|
|
Internation Guest House - Form-work preparation/installation for slab at 3.30 m level |
Internation Guest House - Form-work preparation/installation for slab at 3.30 m level |
Drainage Work (Campus Rejuvanation) |
Form-work preparation/installation for slab at 3.30 m level ( Internation Guest House) |
Excavation for drain & trench in stretch 3-4. (Campus Rejuvanation)
|
|
Campus Rejuvanation Works - Excavation, Shuttering,Reinforcement and PCC |
Campus Rejuvanation Works - Excavation, Shuttering,Reinforcement and PCC |
Excavation for Drain, Trench at Stretch 3-4 (infront of Substation 1) |
Reinforcement installation for Drain in Stretch 1-2.
& P.C.C for drain in stretch 6 to existing drain
|
|
|
|
|