   Weekly Progress Report as on 28.06.2013
    
Progress Report For Kumaranalloore ROB for the week ending on 28-06-2013
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE 33 33 0 0 0 0 0    
2 PILE CAP 11 9 2 0 1 0 0 1  
3 PIER 11 5 6 0 3 0 0 3  
4 PIER CAP 11 5 6 0 0 0 0 0  
                     
                     
                     
                     
 
Back
 
    
LOAD TEST AT P5

    
    
AP2 PILE CAP

    
    
AP1- PI STAGING WORK

      
 

 

 

 

 

 

 

 