   22.10.2010
    
Description Completed/ Progress Remarks
ROB at Payyannur   Work inagurated on 14-9-10
Drawings for Pile & Pile cap  and Sub Structure Approved  
Drawings of Super Structure Approved  
Earth filling for leveling work In progress Slow progress due to rain
Pile Concreting (Total no of piles- 87) In progress Done - 6 no.
     
       
       
       
       
       
 
Back
 
    
TRIKARIPUR SIDE(RAIN)

    
    
PAYYANNUR SIDE

    
    
P3B_ERECTING THE JALI

    
    
P3B- CONCRETING

    
 
    
MATERIALS STACKED FOR CONCRETING

      
 

 

 

 

 

 

 

 