   Weekly Progress as on 14.6.2013
    

 

Progress Report - ROB-Thirunavaya   - 14..06.2013
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 19 2          
7 Expansion Joint 21 18 3   1 1 0 0
8 RC wall - Kuttipuram side 100% 78% 17% - 5% 5% 15% 5%
9 RC wall - Kanjipura side 100% 90% 10%   5% 0% 5% 5%
10 BOX culvert 100% 100% 0%   - - - -
11 CC wall kuttipuram side 100%                  - 50%             - 20% 25%          - 20%
                   
                   
Date 8.06.13 10.06.13 11.06.13 12.06.13 13.06.13 14.06.13      
Climate rain rain rain rain Pleasant rain      
No. of labours 25 25 25 25 25 25      
                   
 