Prevoius Weekly Reports

   weekly progress as on 14.6.2013
    

 

Report For Cheruvathoor  ROB for the week ending on 14-06-2013  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed   Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed   Friction slab capping complete at both RHS&LHS.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0   complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 7 1 0 0 0 0 0   complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed   complete for Friction slab also.
16 KERB PADANNA SIDE 100% 100% Completed   complete for RE Panel portion also.
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed   complete for RE Panel portion also.
18 HANDRAIL PADANNA SIDE 100% 100% Completed   complete for RE Panel portion also.
19 Painting 100% 35% 65% 20% 25% 15% 20% 25%   Work progressing slowly due to shortage of labour and rain.
17 BM/BC 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Bitumen plant is ready but work could not be started due to rain.
18 Others/Miscellaneous                   Drainage works complete for 150 m at chr side.
19 ROAD WORK GSB+WMM IP at Padanna side for 7m service road   WMM 2nd layer complete at chr side beyond zero point of the ROB.
                      Earth cutting complete at Padanna side for both 7m and 4m roads.WMM IP for 7m road.WATER LOGGING DELAYS THE WORK AT 4M ROAD.
                      DR Work complete for 4m service road and 7m road chr side.
                      Hume pipe laying complete at chr side to drain offf rain water
20 Deck Slab                    
 
Back
 
    
PADANNA SIDE-WMM FIRST LAYER COMPLETE FOR 7M ROAD

    
    
PAINTING IP AT PADANNA SIDE

    
    
PADANNA SIDE-WMM FIRST LAYER COMPLETE FOR 7M ROAD

    
    
BITUMEN PLANT

    
 
    
4M SERVICE ROAD AREA PADANNA SIDE WA PIPES BROKEN

      
 

 

 

 

 

 

 

 