   Weekly progress report as on 14.06.2013
    
Progress Report For Mooledam ROB for the week ending on 14-06-2013
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE 21 21 0 0 0 0 0 0 0
2 PILE CAP 7 7 0 0 0 0 0 0 0
3 PIER 9 9 0 0 0 0 0 0 0
4 PIER CAP 9 9 0 0 0 0 0 0 0
5 LOAD TEST 1 1 0 0 0 0 0 0 0
6 ABUTMENT 2 2 0 0 0 0 0 0 0
7 FOOTING 2 2 0 0 0 0 0 0 0
8 GIRDER 9 7 2 0 0 0 0 1 0
9 DECK SLAB 9 7 2 0 0 0 0 1 0
10 PEDESTAL 11 10 1 0 0 0 0 1 0
11 RETAINING WALL  4 0.6 3.4 0 0.1 0 0 0.1 0
 
Back
 
    
P9-AP2 REINFORCEMENT WORKS IN PROGRESS

      
 

 

 

 

 

 

 

 