Edappal Flyover
Project Graph
|
Photo Album
![](sites/all/themes/rbdck2013/images/butn.png) |
Weekly Progress Report - 07.12.2020 to 12.12.2020 |
|
Weekly Progress Report - 07.12.2020 to 12.12.2020 |
07.12.2020 |
08.12.2020 |
09.12.2020 |
10.12.2020 |
11.12.2020 |
12.12.2020 |
Reinforcement work of center span.
|
Reinforcement work of center span. |
Reinforcement work of center span.
|
Shuttering works for Deck slab on Thrissur side |
Shuttering works for Deck slab on Thrissur side
|
Reinforcment works of box girder |
Shuttering work for deck slab at A1-P1 location. |
Shuttering work for deck slab at A1-P1 location. |
Profile work of girder-2 at P3-P4 location |
Reinforcement works for box girder at centre span |
Reinforcement works for box girder at centre span |
Shuttering work of deck slab A1-P1 |
Reinforcement work for diaphragm at A1 location. |
Reinforcement work for diaphragm at A1 location. |
Shuttering work for deck slab at A1 -P1 location |
Reinforcement works for diaphragm at yard |
Reinforcment works of diaphgram |
Reinforcment works of diaphgram |
|
|
Reinforcement work at yard for center span. |
|
|
|
|
|
|
|
|
|
|
|
|