PROGRESS OF ROB WORK AS ON 15.10.2010 |
|
|
|
Description |
Completed/ Progress |
Remarks |
ROB at Sulthan Pet - Palaghat Town |
|
|
Alignment survey |
In progress |
|
Drawings for railway portion and Land spans upto substructure |
Issued on 09-07-10 |
|
Drawings for Land span superstructure |
Issued on 16-09-10 |
|
Construction activities |
Not Started |
|
|
|
|
|