Prevoius Weekly Reports

   Weekly Progress Report as on 31.05.2013
    
Progress Report For Mooledam ROB for the month of May
Sl No  Activity Description  Total Quantity Cumulative progress upto last month  Balance  work up to last month Cumulative delay in Qty up to last month Work  planned  during the month  Actual work done during the month Cumulative delay in Qty up to this month Work  Planned for next month 
1 PILE 21 21 0 0 0 0 0 0
2 PILE CAP 7 7 0 0 0 0 0 0
3 PIER 9 9 0 0 0 0 0 0
4 PIER CAP 9 9 0 0 0 0 0 0
5 LOAD TEST 1 1 0 0 0 0 0 0
6 ABUTMENT 2 2 0 0 0 0 0 0
7 FOOTING 2 2 0 0 0 0 0 0
8 GIRDER 9 5 4 0 3 2 1 2
9 DECK SLAB 9 5 4 0 3 2 1 2
10 RETAINING WALL 4 0.35 4 0 0.65 0.25 0.3 0.3
 