   Weekly Progress Report as on 24.05.2013
    
Si No  Activity Description  Total Quantity Cumulative progress upto 23.05.13 Balance  work up to 23.05.13 Cumulative delay in Qty up to 23.05.13 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 0 0 0 0 completed  
2 PILE Palarivattom side(railway portion) 6 6 0 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0 completed  
4 PILE vytilla side(railway portion) 6 6 0 0 0 0 0 0
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed P15, P14, A2, P13, P12, P11, P10, P9
6 PILE CAP Palarivattom side(railway portion) 1 1 0 0 0 0 0 0 completed RP2
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed P1,  P2, P4, P3, A1, P5,P6, P7,P8
8 PILE CAP vytilla side(railway portion) 1 1 0 0 0 0 0 0 completed RP1
9 PIER Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed A2, P15, P14, P13,  P12,  P11, P10, P9 
10 PIER Palarivattomside(railway portion) 1 1 0 0 0 0 0 0 completed RP2
11 PIER Vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed P1, P2, P3, P4, A1,P5,P6,P7, P8
12 PIER vytilla side(railway portion) 1 1 0 0 0 0 0 0 completed RP1
13 PIER  CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed P15, P14, A2, P13, P12, P11, P10, P9
14 PIER  CAP Vytila side(Approach portion) 9 9 0 0 0 0 0 0 completed P1, P2, P3, A1,P4,P5,P6,P7, P8
15 GIRDER Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11, P10P9, P9RP2
16 GIRDER Vytila side(Approach portion) 9 9 0 0 0 0 0 0 completed P1P2,  A1P1, P2P3, P3P4, P5P6, P6P7, P4P5, P7P8, P8RP1
17 DECK SLAB Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11, P10P9, P9RP2
18 DECK SLABVytila side(Approach portion) 9 9 0 0 0 0 0 0 completed P1P2,A1P1, P2P3, P3P4, P4P5, P5P6, P6P7, P7P8, P8RP1
19 PIER CAP Palarivattomside(railway portion) 1 1 0 0 0 0 0 0 completed RP2
20 PIER CAP vytilla side(railway portion) 1 1 0 0 0 0 0 0 completed RP1
21 RE WALL PANEL CASTING 351 351 0 0 0 0 0 0 completed  
22 RE WALL PCC Palarivattom 95 95 0 0 0 0 0 0 completed  
23 RE WALL Panel erection Palarivattom 100% 100% 0 0 100% 10% 0% 100% completed  
24 RE WALL Earth filling PALARIVATTOM 100% 100% 0 0 100% 0% 0% 0%    
25 RE Wall finishing plrvtm 100% 99% 0.01 1 5% 4% 1% 1%    
26 Rly Pile Load test 1 1 0 0 1 1 0 0 completed  
 