Progress Report For Payyannur ROB-adjacent span work for the week ending on 24-05-2013 |
|
Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
|
1 |
T-junction girder staging |
100% |
100.00% |
complete |
|
2 |
T-junction girder reinforcement |
100% |
100.00% |
complete |
|
3 |
T-junction girder shuttering |
100% |
100% |
complete |
|
4 |
T-junction girder concrete |
1 |
1 |
complete |
|
5 |
T-junction deck slab |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
|
6 |
Standard span P17-RP2 girder |
1 |
1 |
complete |
|
7 |
Standard span P17-RP2 deck slab |
1 |
1 |
complete |
|
8 |
Expansion joints |
2 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
9 |
Kerb |
100% |
0.00% |
0.00% |
30.00% |
30.00% |
30.00% |
0.00% |
70.00% |
|
10 |
Handrail |
100% |
0% |
0.00% |
25.00% |
25.00% |
0.00% |
25.00% |
25.00% |
|
11 |
RC Wall Payyannur side |
100% |
0% |
0.00% |
50.00% |
70.00% |
50.00% |
20.00% |
50.00% |
|
12 |
Toll booth |
100% |
0 |
0 |
0 |
20% |
0 |
20% |
50% |
|
13 |
Stair |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
14 |
BC/PAINTING |
100% |
0.00% |
100% |
0.00% |
0.00% |
0.00% |
0.00% |
0.00% |
|
15 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|