Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888375
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 17.05.2013
    
V ROB at Sulthanpet - Palaghat Town    
  Staging drawing approval from Railways pending 1 no yet to be received (RP3-RP4) 
  Retaining wall (Palakkad side)  In progress 100% work done
  Kerb Casting (Palakkad side) Completed  
  Handrail fixing (Palakkad side) Completed  
  Drain work  (Moyan school  side)  In progress done 40%
  Retaining wall,Kerb & Handrail (Moyan school  side)  Completed 100% completed
  Bowstring girder (RP4-RP5) Completed Done upto bow arch bracing
  Handrail fixing & kerb casting Completed 4 slabs of Moyen's side and 2 slabs of Pkd side completed.
  Bowstring girder Stressing and grouting Completed  
  RP6-RP7-RP8 railway slab Completed  
  RP6-RP7-RP8 Kerb & paparapet wall Completed  
  RP7-P5, P5-P6, P6-P7, P7-P8 Deck slab and girder completed Moyen's school side deck slabs
  Crash barier for RP6-RP7-RP8 Completed  
  P1-P2, P4-RP1 Deck slabs and girder Completed Pkd side deck slabs
  RP5-RP6 girder & deck slab work Completed  
  RP5-RP6 Crash barrier  Completed  
  RP5-RP6 Kerb & paparpet wall Completed  
  RP4-RP5 Deck slab casting Completed Bowstring girder
  RP4-RP5 slab lowering Completed  
  RP4-RP5 crash barrier/kerb casting In progress  
  Approach filling Completed Moyen's school side & Pkd side
  WBM for approach Completed Moyen's school side & palakkad side
  Cantilver portion of P7-P8 & P1-P2 completed  
  Diversion road WBM Completed Moyens side
  Painting works Stopped Moyens & Palakkad side
  Ret wall LHS & RHS side I, II & III port In progress III arm
  Piling works in P10, P11, P12 locations Completed III arm (12 No.s)
  Pile cap works in P10 P11 & P12 location Completed III arm 
  Pier P10 P11 & P12 Completed  
  RP8-P9 girder and deck slab casting Completed  
  RP1-RP2 girder and slab casting Completed  
  RP1-RP2 stressing and grouting Completed  
  RP2-RP3 Stressing Completed  
  Pier cap P10, P11, P12 Completed  
  P9-P10 & P10-P11 girder and slab casting Completed  
  RP2-RP3 Girder & slab work Completed  
  RP3-RP4 temp. footing In progress 45% done
  P11-P12 girder & slab casting Completed  
 
Back

No images are uploaded for this Weekly Reports

 
 
 

 

 

 

 

 

 

 

Untitled Document