PROGRESS OF ROB WORK AS ON 15.10.2010
  Description Completed/ Progress Remarks
       
V ROB at Payyannur   Work inagurated on 14-9-10
  GAD Approved  
  Drawings for Pile & Pile cap  and Sub Structure Approved  
  Drawings of Super Structure Approved  
  Earth filling for leveling work In progress Slow progress
  Pile Concreting (Total no of piles- 87) Done - 4 no.   

 

 
Back
 
    
WORK-AT1AM-P3A

    
    
JALI-WORK-IN-PROGRESS

    
    
ERECTING-THE-STEEL-JALI-P6A

    
    
CONCRETING_P6_B

    
 
    
CONCRETING_P3A

      
 

 

 

 

 

 

 

 