   15.10.2010
    
PROGRESS OF ROB WORK AS ON 15.10.2010
  Description Completed/ Progress Remarks
  ROB at Mulankunnathukavu   Work inagurated on 13-9-10
  GAD Approved  
  SubStructure & Foundation Drg Approved  
  Super Structure Drg Approved  
  Pile Concreting (Total no of piles- 45) Done - 1 no.   
   

 

 