15.10.2010 |
|
PROGRESS OF ROB WORK AS ON 15.10.2010 |
|
Description |
Completed/ Progress |
Remarks |
|
ROB at Mulankunnathukavu |
|
Work inagurated on 13-9-10 |
|
GAD |
Approved |
|
|
SubStructure & Foundation Drg |
Approved |
|
|
Super Structure Drg |
Approved |
|
|
Pile Concreting (Total no of piles- 45) |
Done - 1 no. |
|
|
|
|
|
|