   Weekly Progress Report as on 10.05.2013
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed  
2 PILE PADANNA SIDE 24 24 Completed  
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed  
4 PILE CAP  PADANNA SIDE 8 8 Completed  
5 PIER CHERUVATHOOR SIDE 9 9 Completed  
6 PIER PADANNA SIDE 8 8 Completed  
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed  
8 PIER CAP PADANNA SIDE 8 8 Completed  
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed Friction slab capping complete at both RHS&LHS.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span  
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span  
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0 complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 7 1 0 0 0 0 0 complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed complete for Friction slab also.
16 KERB PADANNA SIDE 100% 100% Completed complete for RE Panel portion also.
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed complete for RE Panel portion also.
18 HANDRAIL PADANNA SIDE 100% 100% Completed complete for RE Panel portion also.
19 Painting 100% 15% 85% 40% 0% 0% 20% 0% Painting started at cheruvathur side.1st coat complete for the girders AP2-P8.Works held up due to shotrage of painting materials
17 BM/BC 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% Plant to reach site after bitumen works at Parappanangadi.
18 Others/Miscellaneous                 Drainage works complete for 150 m at chr side.
19 ROAD WORK GSB+WMM Works resumed on 18.03.13 WMM 2nd layer complete at chr side beyond zero point of the ROB
                    Earth cutting complete at Padanna side for both 7m and 4m roads
                    DR Work complete for 4m service road and 7m road chr side.
                     
20 Deck Slab                  
21 Utility shifting                  
                     
                     
                     
  Availbility of Men                   
  Date 5/4/2013 5/5/2013 5/6/2013 5/7/2013 5/8/2013 5/9/2013 5/10/2013    
  No of labours 3 3 3 10 10 10 10    
                     
  Material Stocking Status Required Available Remarks            
  Coarse Aggreagate (m3) available              
  Fine Aggreagate(m3) available            
  Cement(bag) 0 20            
  Steel(MT) 0 0.3            
 