   Weekly Progress Report as on 10.05.2013
    
Progress Report For Payyannur ROB-adjacent span work for the week ending on 10-05-2013  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 T-junction girder staging 100% 100.00% complete    
2 T-junction girder reinforcement 100% 100.00% complete   Reinforcement complete
3 T-junction girder shuttering 100% 100% complete    
4 T-junction girder concrete 1 1 complete   concreted  on 29.04.13
5 T-junction deck slab 1 0 0 0 1 0 1 1   Planned on 13.05.13
6 Standard span P17-RP2 girder 1 1 complete   concreted on 26.03.13
7 Standard span P17-RP2 deck slab 1 1 complete   concreted on 30.03.13
8 Expansion joints 2 0 0 0 0 0 0 1   P17 planned
9 Kerb  100% 0.00% 0.00% 30.00% 30.00% 30.00% 0.00% 70.00%   RP2-P17 kerb concreted
10 Handrail 100% 0% 0.00% 25.00% 25.00% 0.00% 25.00% 25.00%   RP2-P17 Planned
11 RC Wall Payyannur side 100% 0% 0.00% 50.00% 70.00% 50.00% 20.00% 50.00%   wall concreted for 14m
12 Toll booth 100% 0 0 0 20% 0 20% 50%   Planned this week
13 Stair 4 0 0 0 0 0 0 0    
14 BC/PAINTING 100% 0.00% 100% 0.00% 0.00% 0.00% 0.00% 0.00%    
15 Others/Miscellaneous                    
 
Back
 
    
T-JUNCTION DECK SLAB REINFORCEMENT IN PROGRESS

    
    
RP2-P17 SPAN KERB CONCRETE

      
 

 

 

 

 

 

 

 