PROGRESS OF ROB WORK AS ON 15.10.2010
  Description Completed/ Progress Remarks
I ROB Koratty    
  Design and Drawing for Railway span Submitted Approval pending with Railways
  Retaining wall concreting In progress  
  RE Wall work near Under Pass In progress  
  Asphalting work of old road under ROB Completed   
   

 

 

 