Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
100% |
Completed |
Friction slab and capping complete at both sides. |
10 |
RE/RC WALL PADANNA SIDE |
100% |
100% |
Completed |
Friction slab capping complete at both RHS&LHS. |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
8 |
1 |
complete except railway adjacent span |
|
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
8 |
1 |
0 |
0 |
0 |
0 |
0 |
complete except P8 |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
7 |
1 |
0 |
0 |
0 |
0 |
0 |
complete except P7 |
15 |
KERB CHERUVATHOOR SIDE |
100% |
100.00% |
Completed |
complete for Friction slab also. |
16 |
KERB PADANNA SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
18 |
HANDRAIL PADANNA SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
19 |
Painting |
100% |
15% |
85% |
15% |
20% |
5% |
15% |
0% |
Painting started at cheruvathur side.1st coat complete for the girders AP2-P8.Works held up due to shotrage of painting materials |
17 |
BM/BC |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
Plant to reach site after bitumen works at Parappanangadi. |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
Drainage works complete for 150 m at chr side. |
19 |
ROAD WORK |
GSB+WMM Works resumed on 18.03.13 |
WORKS HELD UP DUE TO JCB COMPLAINT.WMM 2nd layer complete at Padanna approach |
|
|
|
|
|
|
|
|
|
|
Earth cutting complete at Padanna side for both 7m and 4m roads |
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and 7m road chr side. |