   Weekly progress
    
PROGRESS OF ROB WORK AS ON 15.10.2010
  Description Completed/ Progress Remarks
I ROB at Parappanangady   Work inagurated on 13-9-10
  GAD Approved  
  SubStructure & Foundation Drg Approved  
  Super Structure Drg Not Submitted  
  Construction activities Not Started   
   

 

 
Back
 
    
TRIPOD RAISED FOR P-16 PILE

    
    
TRIPOD RAISED FOR P-13 PILE

    
    
ALIGNMENT OF PARAPPANAGADY ROB

    
    
ALIGNMENT OF PARAPPANAGADY ROB.

    
 
    
ALIGNMENT CLEARING AT PARAPPANAGADY ROB.

    
    
ALIGNMENT CLEARING AT PARAPPANAGADY ROB..

      
 

 

 

 

 

 

 

 