Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887726
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 26.04.2013
    
Progress Report For Mooledam ROB for the month of April
Sl No  Activity Description  Total Quantity Cumulative progress upto last month  Balance  work up to last month Cumulative delay in Qty up to last month Work  planned  during the month  Actual work done during the month Cumulative delay in Qty up to this month Work  Planned for next month  No of days remaing for completion as per the weekly plan
1 PILE 21 21 0 0 0 0 0 0 0
2 PILE CAP 7 7 0 0 0 0 0 0 0
3 PIER 9 9 0 0 0 0 0 0 0
4 PIER CAP 9 9 0 0 0 0 0 0 0
5 LOAD TEST 1 1 0 0 0 0 0 0 0
6 ABUTMENT 2 2 0 0 0 0 0 0 0
7 FOOTING 2 2 0 0 0 0 0 0 0
8 GIRDER 9 4 5 0 2 1 1 3 0
9 DECK SLAB 9 4 5 0 2 1 1 3 0
10 RETAINING WALL 4 0.1 4 0 0.5 0.25 0.25 0.65 0
 
Back
 
    
COMPLETED SPAN P5-P6

    
    
DECK SLAB P1-P2 READY

    
    
DECK SLAB P1-P2 READY

      
 

 

 

 

 

 

 

 

Untitled Document