Prevoius Weekly Reports

   weekly progress as on 19.4.2013
    

 

Progress Report For Mooledam ROB for the week ending on 20-04-2013
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE 21 21 0 0 0 0 0 0 0
2 PILE CAP 7 7 0 0 0 0 0 0 0
3 PIER 9 9 0 1 0 0 0 0 0
4 PIER CAP 9 9 0 0 0 0 0 0 0
5 LOAD TEST 1 1 0 0 0 0 0 0 0
6 ABUTMENT 2 2 0 0 0 0 0 0 0
7 FOOTING 2 2 0 0 0 0 0 0 0
8 GIRDER 9 4 5 0 0 0 0 0 0
9 DECK SLAB 9 4 5 0 0 0 0 0 0
10 PEDESTAL 9 5 4 0 3 3 0 0 0
11 RETAINING WALL  4 0.1 3.9 0 0.15 0.15 0 0.2 0
12 RETAINING WALL raft 4 0.6 3.4 0 0.25 0.25 0 0.15 0
                     
                     
  Availbility of Men                   
  Date 13/4/2013 15/4/2013 16/4/2013 17/4/2013 18/4/2013 19/4/2013      
  Nof labours 25 25 25 6 25 25      
                     
  Material Stocking Status                
    Required Available Remarks            
  Fine aggregate {cft} 150 0              
  Cement(bag) 50 200              
  Steel in T 15 25              
  Coarse Aggreagate (cft) 150 300              
                     
  Utility shifting                  
  Utilities to be shifted   Remarks              
  BSNL   Shifting  required              
  KSEB   Shifting started              
  KWA   Shifting required              
  Others                  
 