Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888125
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress as on 19.4.2013
    

 

Progress Report - ROB-Thirunavaya   - 19.04.2013
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 19 2          
7 Expansion Joint 21 18 3   1 1 0 0
8 RC wall - Kuttipuram side 100% 78% 22% - 15% 0% 15% 15%
9 RC wall - Kanjipura side 100% 90% 10%   5% 5% 0% 5%
10 BOX culvert 100% 50% 50%   25% 25% 0% 30%
                   
Date 13.04.13 15.04.13 16.04.13 17.04.13 18.04.13 19.04.13      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 20 20 20 20 20 20      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 18 m3 22 m3              
Coarse Aggregate 30 m3  34 m3              
Cement 200 bags 300 bags              
Steel 15MT 28 MT              
 
Back
 
    
RC WALL AT KUTTIPURAM SIDE

    
    
BOX CULVERT WORK AT KUTTIPURAM SIDE

      
 

 

 

 

 

 

 

 

Untitled Document