Progress Report For Koilandy ROB for the week ending on 12-04-2013 |
|
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE Muthambi side |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
2 |
PILE Thamarassery side |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
3 |
PILE NH SIDE |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
4 |
PILE CAP Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
5 |
PILE CAP Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
6 |
PILE CAP NH SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
7 |
PIER Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
8 |
PIER Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
9 |
PIER NH SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
10 |
PIER CAP Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
11 |
PIER CAP Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
12 |
PIER CAP NH SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
13 |
RE/R WALL Muthambi side |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0 |
0.00% |
Completed |
14 |
RE/R WALL Thamarassery side SIDE |
100% |
97% |
3% |
0 |
3.00% |
3.00% |
0 |
0.00% |
Completed |
15 |
RE/R WALL NH SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0 |
0.00% |
completed. |
16 |
BEAM/SLAB Muthambi SIDE |
8 |
8 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
17 |
BEAM/SLAB Thamarassery SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
18 |
BEAM/SLAB NH SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
19 |
HR/FP/KERB Muthambi SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0 |
0.00% |
Completed |
20 |
HR/FP/KERB thamarassery SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0 |
0.00% |
Completed |
21 |
HR/FP/KERB NH SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0 |
0.00% |
Completed |
22 |
PAINTING |
100% |
95% |
5% |
0 |
5.00% |
3.00% |
0.02 |
2.00% |
in progress. Only few touching works in balance |
23 |
Mastic Work |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0 |
0.00% |
Completed |
23 |
Utility shifting |
|
|
|
|
|
|
0 |
|
KSEB utility shifting started. Only 1 post remaining to shift |