Prevoius Weekly Reports

   Weekly Progress as on 12.04.2013
    
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards Kadukutty side 27 27 0 0 0 0 0 0  
2 Pile towards Divine Centre side 18 18 0 0 0 0 0 0  
3 Pile cap at Kadukutty  Side 8 8 0 0 1 1 0 0  
4 Pile Cap at Divine centreside 5 3 2 0 0 0 1 1  
5 RC wall at Kadukutty side 100% 0% 1 0 0 0 0 0  
6 RC wall at Divine centre side 100% 0% 1 0 0 0 0 0  
7 Pier at Kadukutty Side 8 6 2 2 0 0 0 1 1st lift of p6a completed
8 Pier at Divine centre Side 5 2 3 2 1 1 0 1 p7 and p8 completed
9 Piercap at Kadukutty Side 8 6 2 3 0 0 3 0  
10 Piercap at Divine centre 5 2 3 3 1 1 0 1  
11 PEDESTAL 48 4 44 44 0 0 44 0  
12 Beam and cross beam at Kadukutty side 7 0 7 7 1 0 1 0  
13 Beam and cross beam at Divine centre side  4 0 4 0 0 0 0 0  
14 Deck slab  at Kadukutty side  7 0 7 0 1 0 1 0  
15 Deck slab  at Divine centre side  4 0 4 0 0 0 0 0  
16 Dirt wall  2 0 2 0 0 0 0 0  
17 Kerb Kadukutty side 100% 0% 100% 0% 0% 0% 0% 0%  
18 Kerb Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
19 Earth filling in approach embankment  100% 0% 100% 0% 0% 0% 0% 0%  
20 Hand rail fixing -Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
21 Hand rail fixing -Kadukutty side 100% 0% 100% 0% 0% 0% 0% 0%  
22 Expansion Joints 12 0 7 0% 0% 0% 0% 0%  
23 WBM  100% 0% 100% 0 0% 0% 0% 0%  
24 Acrylic Elastomeric Membrane Coating 100% 0% 100% 0 0% 0% 0% 0%  
 