   Weekly Progress Report as on 12.04.2013
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 19 2          
7 Expansion Joint 21 18 3   1 1 0 0
8 RC wall - Kuttipuram side 100% 78% 22% - 15% 0% 15% 15%
9 RC wall - Kanjipura side 100% 90% 10%   5% 5% 0% 5%
10 BOX culvert 100% 25% 75%   20% 10% 10% 25%
                   
Date 06.04.13 08.04.13 09.04.13 10.04.13 11.04.13 12.04.13      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 10 10 10 10 10 10      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 15 m3 10 m3              
Coarse Aggregate 32 m3  14 m3              
Cement 150 bags 0 bags              
Steel 10MT 25 MT              
 
Back
 
    
RC WALL AT KUTTIPURAM SIDE

    
    
BOX CULVERT.

      
 

 

 

 

 

 

 

 